We have semi-finished product production order, with the material price control as "V". At the time of production order creation current moving average price is taken as planned price in the order. We done the GRN against the order but reversed the GRN. We have changed the moving average price using MR21 and done the GRN again. But system is still taking the planned price from the order and not the moving average price. The "goods received valuation for the order delivery is maintained with valuation variant "0007:The valuation variant settings for the plant is maintain as "valuation price accordingly to material master". Please advise why the moving average price is not taken while doing the GRN against the production order.