Hi Experts,
My question is related to the following forums -
http://scn.sap.com/thread/1937863
http://scn.sap.com/thread/962249
I know that MRP result can be found in MD05 / MD06, but it could only be found the latest result. According to the above 1st Forum, the older MRP List(s) could still be found in SP01, but the SP01 data can only be found within 9 days in our company. For this case, does it mean that I cannot search the MRP result for records older than 9 days, including the related planned order(s) ?
Also, the "Planned Mode" of our MRP criteria is set as "3 - Delete and recreate planning data". Does it mean that the Planned Order(s) deleted by MRP run (due to no requirement for the materials) cannot be searched thr COOIS or elsewhere ?
Tks,
KH Fong