2 Activity Rates Calculation on one Cost Element

$
0
0

Hi All,

 

We have  a requirement from our business. We have three production activities...

 

Direct Labour

Utilities

Setup

 

As they have cost elements for Direct Labour & Utilities and no cost element for Setup. The cost element planning is done on Direct Labour & Utilities and not on Setup.

 

Activity hours are done on all the three activities.

 

Now business wants to arrive at an Direct labour activity rate based on the following formula...

 

Budget Direct Labour Cost/ Direct Labour Hrs+ Setup Hrs..

 

Is this possible in SAP.

 